From design to building permit: how the approval cycle of a development works
In Itapema and Porto Belo, the path from design to construction start takes 12 to 14 months. We explain each stage.

Before construction begins, every development goes through an approval cycle with the city government and environmental agencies. In Itapema and Porto Belo, this process takes 12 to 14 months on average.
It all starts with the design and a preliminary review. Next comes the filing with the city government, which produces the compliance report. After that, the complementary designs are approved, such as plumbing and sanitation, fire prevention and the preliminary environmental license.
Once the complementary designs are approved, the city gives final approval to the architectural design and the environmental installation license is issued. Finally, municipal fees and the outorga onerosa (a charge for additional building rights) are paid, when applicable, and the building permit is issued, the official document that authorizes construction to begin.
At LG, this cycle is managed together with Hartmann Arquitetos e Associados, our partner on the designs. That is why every launch only reaches the public with its legal path clearly defined.